What makes a Party Wall Notice valid?
5 November 2022

A Party Wall Notice is only as useful as it is valid. A notice with missing information, the wrong owner's name or an incorrect method of service can be challenged, and the result is usually delay while a fresh notice is served and a new notice period runs. A little care at the outset avoids that.
The short answer
A Party Wall Notice is valid when it is the correct type for the works, contains the information the Party Wall etc. Act 1996 stipulates, is served on every Adjoining Owner and is served by a method permitted under Section 15. A Party Structure Notice must state the owner's name and address, the nature and particulars of the works and a start date, as Section 3 stipulates. A Section 6 notice must include plans and sections.
Below, our Chartered Surveyors in North London explain what a valid notice must contain, how it may be served and the defects we see most often.
What must a valid Party Wall Notice contain?
A valid notice must contain the particular information the Act stipulates for that type of notice, along with the correct names of the owners and the address of the property affected. Each type of notice has its own requirements.
Line of Junction Notice (Section 1)
A Line of Junction Notice must describe the intended wall and be served at least one month before the work starts. It should make clear whether you propose to build the wall astride the boundary or wholly on your own land.
Party Structure Notice (Section 3)
Section 3 of the Act stipulates that a Party Structure Notice must state the name and address of the Building Owner, the nature and particulars of the proposed work, including details of any special foundations along with plans, sections and particulars of their construction, and the date on which the work will begin. It must be served at least two months before that date.
Notice of Adjacent Excavation (Section 6)
A Section 6 notice must state whether the Building Owner proposes to underpin or otherwise strengthen or safeguard the foundations of the neighbouring building. It must be accompanied by plans and sections showing the site and depth of the excavation and the site of any building proposed. It must be served at least one month before the excavation starts.
Who must the notice be served on?
A notice must be served on every Adjoining Owner affected by the works. Under the Act, an owner includes the freeholder and anyone holding a lease of more than a year, so a single property can have more than one owner who needs a notice.
Checking ownership is one of the most important steps. A Land Registry search confirms who owns the freehold and whether there are registered leases. Where a property is jointly owned, the notice should name all the owners. A notice served on a tenant with a short tenancy, or addressed to the wrong person, is a common reason a notice fails.
How can a Party Wall Notice be served?
Section 15 of the Act sets out the permitted methods of service. A notice can be delivered to the owner in person, sent by post to their usual or last known residence or place of business, or, for a company, delivered to its registered or principal office.
Where a notice is served on someone as the owner of premises, it can also be addressed to "the owner" of those premises, naming the premises, and delivered to a person there or, if no one is there, fixed to a conspicuous part of the premises.
Electronic service by email is only valid where the recipient has agreed to receive notices that way. Without that agreement, an emailed notice should not be relied upon. We recommend keeping proof of postage or delivery, as the date of service starts the notice period.
What are the most common defects in Party Wall Notices?
The most common defects are the wrong type of notice, incorrect owner details and missing information. In our experience, the following crop up regularly:
- Serving a "Section 2 notice". Section 2 lists the rights a Building Owner has over a party wall, but the notice for those works is a Party Structure Notice served under Section 3.
- Naming only one of several joint owners, or missing a leaseholder or freeholder altogether.
- Omitting the start date from a Party Structure Notice, or giving a date that does not allow the full two months.
- Serving a Section 6 notice without plans and sections, or without stating whether underpinning is proposed.
- Describing the works so vaguely that the neighbour cannot understand what is intended.
- Serving by email without the recipient's prior agreement.
- Serving one type of notice when the works trigger two or three.
Structural calculations are not something the Act stipulates for a notice itself, although the surveyors will usually ask for them later when preparing the Party Wall Award.
What happens if a Party Wall Notice is invalid?
If a notice is invalid, the procedure it was meant to start may not have started at all. The Building Owner may need to serve a fresh notice and wait for a new notice period to run, which can delay the project.
An invalid notice can also undermine any surveyor appointments and Party Wall Award that follow from it. Starting notifiable work without valid notice exposes the Building Owner to the risk of an injunction and a claim from the neighbour. Our guide on what happens if you build without a Party Wall Agreement explains the consequences.
Does a Party Wall Notice expire?
Yes. A Party Structure Notice or a Notice of Adjacent Excavation lapses if the works have not begun within 12 months of service, under Section 3(2)(b) and Section 6(8) of the Act. A new notice would then be needed.
Frequently asked questions
Can I write my own Party Wall Notice?
Yes. A Building Owner can prepare and serve their own Party Wall Notice. It is sensible to include an acknowledgement form so the neighbour can easily consent or dissent, and to check the content carefully against the Act before serving.
Does my neighbour need to agree for the notice to be valid?
No. Validity depends on the content and service of the notice, not on the neighbour's response. If they dissent or do not respond, surveyors are appointed to resolve the matter under Section 10.
Does the notice set out working hours and record the condition of my neighbour's property?
No. Those matters are dealt with in the Party Wall Award, which is prepared by the surveyors after notice has been served. The Award usually includes a Schedule of Condition. Our guide to what a Party Wall Notice is explains how the notice fits into the wider process.
Speak to a Chartered party wall surveyor in North London
A valid notice is the starting point for everything that follows, and it is far easier to get right first time than to correct later.
Hudson Party Wall Surveyors is a Chartered, RICS-regulated practice based in North Finchley, acting for Building Owners and Adjoining Owners across North London. We prepare and serve notices, carry out Schedules of Condition and prepare Party Wall Awards. To discuss your project, call Simon on 020 3488 7747 or email simon@hudsonpartywallsurveyors.co.uk.
Need help with your Party Wall Matters?
We’re here to help. Call for free advice or book a Chartered Party Wall Surveyor to call you at your convenience.