What happens if you build without a Party Wall Agreement?
18 May 2022

It can be tempting to think that work on your own property is your own business. Where the works affect a shared wall or involve digging close to a neighbour's foundations, that is not the case. The Party Wall etc. Act 1996 sets out a procedure that must be followed before notifiable works begin. So what happens if you build without a Party Wall Agreement?
The short answer
If you carry out notifiable works without serving notice under the Party Wall etc. Act 1996, and without written consent or a Party Wall Award, you lose the Act's protection. Your neighbour can seek a court injunction to stop the works and claim damages at common law for nuisance or trespass. The statutory rights the Act gives a Building Owner under Sections 2 and 6 depend on notice being served first.
What is a Party Wall Agreement?
"Party Wall Agreement" is the term most people search for, but the formal document under the Act is a Party Wall Award. It is made by the surveyors appointed under Section 10, not negotiated between neighbours.
Where the Adjoining Owner gives written consent to a notice, no Award is needed. Where they dissent, or do not reply within 14 days, a dispute arises and the surveyors make an Award setting out the works, how they will be carried out, working hours, access and how any damage will be dealt with. It is not a request for permission. The Act gives the Building Owner rights to carry out certain works, provided the procedure is followed. Our guide on what you should know about Party Wall Agreements explains the document in more detail.
Which works need a Party Wall Notice?
The Act applies to three broad categories of work, each with its own notice:
- Section 1, Line of Junction Notice: a new wall on or astride the boundary. One month's notice.
- Section 3, Party Structure Notice: works to an existing party wall listed in Section 2, such as cutting in steel beams, raising the wall or removing a chimney breast. Two months' notice.
- Section 6, Notice of Adjacent Excavation: digging within 3 metres of a neighbour's building to a lower depth than their foundations, or within 6 metres where the excavation would cut a 45-degree line drawn down from the bottom of their foundations. One month's notice.
If you are unsure whether your project is covered, our guide on what a Party Wall Notice is sets out the basics.
Can building work start without a Party Wall Agreement?
Not lawfully, where the works are notifiable. You need either the Adjoining Owner's written consent or a served Party Wall Award before those works begin.
A common misunderstanding is that a neighbour's silence allows work to start. It does not. If your neighbour has not replied within 14 days, a dispute is deemed to have arisen, and surveyors must be appointed. Starting work at that point is no different from starting without notice.
What can my neighbour do if I build without notice?
They can go to court. Without a notice, the works are not authorised by the Act, and the Adjoining Owner's remedies lie at common law.
Injunction
An Adjoining Owner can apply to the court for an injunction to stop the works. An injunction can halt a project part way through, leaving the Building Owner with idle contractors, extra cost and delay, as well as their own legal fees.
Claims for damage, nuisance and trespass
If damage is alleged, there is no Schedule of Condition recording the neighbour's property before the works began. That makes it much harder to show which cracks were already there. In Power & Kyson v Shah [2023] EWCA Civ 239, the Court of Appeal confirmed that where no notice has been served, the Act's dispute procedure does not apply and the neighbour's claim proceeds under the ordinary law. Our article on an Adjoining Owner's rights if damage occurs explains how damage is normally handled under an Award.
Problems when you come to sell
Buyers' solicitors routinely ask whether party wall procedures were followed for past works. Missing paperwork can cause questions and delay at the point of sale.
Can I put things right if work has already started?
Often, yes. If you realise part way through that the works were notifiable, stop the relevant works and take advice. A surveyor can serve the correct notices and, if the neighbour dissents, an Award can be made for the remaining works. Damage that has already occurred may need to be dealt with separately, which is one reason it is far better to start correctly.
Does planning permission or Building Regulations approval cover party wall matters?
No. Planning permission, permitted development and Building Regulations are entirely separate from the Party Wall etc. Act 1996. Having planning permission, or a Building Control sign off, does not remove the need to serve notice.
Frequently asked questions
Is building without a Party Wall Agreement a criminal offence?
Generally not. The consequences are civil: injunctions, damages claims and costs. They can still be serious and expensive.
Do I need a Party Wall Agreement if my neighbour is happy with the works?
You still need to serve notice. If your neighbour consents in writing, no Award is needed, though many owners still choose to record the condition of the neighbouring property first.
Does a loft conversion always need a Party Wall Agreement?
Not always. A loft conversion often involves cutting beams into a party wall, which is work listed in Section 2 and notified by a Party Structure Notice under Section 3. A loft conversion on its own does not involve excavation, so Section 6 does not apply.
Who pays for the Party Wall Award?
Generally the Building Owner, under Section 11, because the works are for their benefit.
Speak to a Chartered party wall surveyor in North London
Building without notice can turn a straightforward project into a contested one. Serving the right notice at the right time is quicker and cheaper than dealing with an injunction or an unrecorded damage claim.
Hudson Party Wall Surveyors is a Chartered, RICS-regulated practice based in North Finchley, acting for Building Owners and Adjoining Owners across North London. You can read more about serving a Party Wall Notice on our website. To discuss your project, call Simon on 020 3488 7747 or email simon@hudsonpartywallsurveyors.co.uk.
Need help with your Party Wall Matters?
We’re here to help. Call for free advice or book a Chartered Party Wall Surveyor to call you at your convenience.