Three common renovation works that affect Party Walls
13 February 2023

If you are planning renovation works to a terraced or semi-detached house, there is a good chance the Party Wall etc. Act 1996 applies. In North London, three projects account for most of the party wall matters we see: loft conversions, rear extensions and chimney breast removals. Each affects your neighbour in a different way, and each triggers a different notice under the Act.
The short answer
Under the Party Wall etc. Act 1996, a loft conversion usually needs a Party Structure Notice under Section 3, as beams are cut into the party wall. A rear extension often needs a Notice of Adjacent Excavation under Section 6 for its foundations, and a Line of Junction Notice under Section 1 if a new wall is built on the boundary. Chimney breast removal needs a Party Structure Notice under Section 3.
Below, we look at each type of work in turn, which notice it triggers, how much notice the Act stipulates and what else to consider.
What counts as a party wall?
A party wall is a wall that stands on the land of two owners and forms part of a building, or a wall that separates buildings belonging to different owners, even where it stands wholly on one owner's land. The walls between terraced and semi-detached houses are the most common examples.
The Act also covers party fence walls, which are garden walls standing astride the boundary that do not form part of a building, and party structures such as the floors between flats. A garden wall built wholly on one owner's land is not a party fence wall.
Does a loft conversion need a Party Wall Notice?
Most loft conversions need a Party Structure Notice under Section 3, because the works usually involve the party wall. Typical notifiable works include cutting into the party wall to bear new steel beams, raising the party wall to form a dormer or mansard, removing chimney breasts at loft level and cutting in flashings.
Section 2 of the Act sets out these rights, and the notice for them is served under Section 3. The Act stipulates at least two months' notice before the works begin. The notice must state the nature and particulars of the proposed work and the date on which it will start.
A loft conversion on its own does not trigger Section 6, because no excavation is involved. If the project also includes new foundations, for example for a rear extension at the same time, a separate notice may be needed for that part. Our guide to Party Wall Agreements for loft conversions looks at loft projects in more detail, and our article on steel beams and Party Wall Notices covers beam bearings specifically.
Does a rear extension need a Party Wall Notice?
A rear extension often needs one or more notices, depending on where the foundations and walls are built. The three most common triggers are excavation, a new wall on the boundary and works to the existing party wall.
Excavation for foundations (Section 6)
A Notice of Adjacent Excavation is needed where you will excavate within 3 metres of your neighbour's building or structure and to a lower depth than the bottom of its foundations. It is also needed within 6 metres where the excavation would cut a line drawn downwards at 45 degrees from the bottom of the neighbour's foundations. The Act stipulates at least one month's notice, and the notice must include plans and sections showing the site and depth of the excavation.
New extension foundations are frequently deeper than those of older neighbouring houses, which is why Section 6 so often applies. Your structural engineer's drawings will show the proposed foundation depth.
A new wall on the boundary (Section 1)
If the flank wall of the extension is to be built on or astride the line of junction between the two properties, a Line of Junction Notice is needed under Section 1, with at least one month's notice. A wall can only be built astride the boundary with the neighbour's consent.
Works to the existing party wall (Section 3)
Where the extension involves cutting into the existing party wall, for example to insert a beam, tie in new work or cut in flashings, a Party Structure Notice is also needed. Works to a shared garden wall that is a party fence wall, such as demolishing or raising it, can also fall under this section.
Does removing a chimney breast need a Party Wall Notice?
Yes. Removing a chimney breast attached to a party wall is a notifiable work, and a Party Structure Notice must be served under Section 3 with at least two months' notice.
Chimney breasts are often shared or back on to a neighbour's flue, so removal can affect the stability of the wall and the remaining stack. The remaining structure must be properly supported, and that design is a matter for your structural engineer and Building Control. Our guide to chimney breast removal and the Party Wall Act explains the process in more depth.
What happens after the notice is served?
Your neighbour has 14 days to respond. They can consent, or dissent, in which case surveyors are appointed under Section 10. If they do not respond within 14 days, a dispute is deemed to have arisen. The surveyors then prepare a Party Wall Award, which usually includes a Schedule of Condition of the neighbouring property.
A notice lapses if the works have not begun within 12 months of service, so it is best to serve notice once your plans and start date are reasonably settled.
Frequently asked questions
Does planning permission cover the party wall side of things?
No. Planning permission, permitted development and Building Regulations are separate from the Party Wall etc. Act 1996. Even where your project is permitted development, you may still need to serve a Party Wall Notice.
Can one project need more than one notice?
Yes. A combined loft conversion and rear extension commonly needs a Party Structure Notice, a Notice of Adjacent Excavation and sometimes a Line of Junction Notice, served on each affected neighbour.
Do I need to serve notice for internal works such as replastering or rewiring?
Generally not. Minor works such as fixing shelves, replastering or chasing in electrical cables are not usually notifiable. If you are unsure whether your work involves cutting into the wall in a way the Act covers, it is worth checking before you start.
Speak to a Chartered party wall surveyor in North London
Identifying the right notices early keeps your project on programme and gives your neighbours clear information from the start. You can read more about our Party Wall Notice service.
Hudson Party Wall Surveyors is a Chartered, RICS-regulated practice based in North Finchley, acting for Building Owners and Adjoining Owners across North London. We regularly advise on loft conversions, rear extensions and chimney breast removals. To discuss your plans, call Simon on 020 3488 7747 or email simon@hudsonpartywallsurveyors.co.uk.