The difference between a Party Wall Award and Schedule of Conditions
31 August 2022

When you are planning work to your property, or your neighbour is, it is easy to be confused by the paperwork. Two documents come up more than most: the Party Wall Award and the Schedule of Condition. They are closely linked and often sit in the same bundle, but they do different jobs. Working with an experienced RICS surveyor in North London takes much of the confusion out of it.
The short answer
A Party Wall Award is the legally binding document made by the surveyors under Section 10 of the Party Wall etc. Act 1996 when a dispute arises, setting out what work may be done, how and when. A Schedule of Condition is a factual record of the Adjoining Owner's property before the works start. The Award governs the works; the Schedule is the evidence used if damage is later claimed.
Below, we explain what each document is, when you need it and how the two work together.
What is a Party Wall Award?
A Party Wall Award is a formal decision made by the appointed surveyors that resolves the dispute between the Building Owner and the Adjoining Owner about the notifiable works. It is often called a Party Wall Agreement, although strictly it is an Award made under Section 10 of the Act.
A typical Award sets out:
- a description of the works and the drawings they must follow
- the right to carry out those works and how they are to be done
- working hours and other practical controls
- access arrangements for the surveyors
- the surveyors' fees and who pays them
The Award is binding on both owners. Either owner can appeal to the County Court within 14 days of it being served, under Section 10(17) of the Act.
Do I legally need a Party Wall Award?
Not always. You need one only if your works are notifiable under the Act and the Adjoining Owner does not consent in writing. If they consent, no Award is needed. If they dissent, or do not respond within 14 days, a dispute is deemed to have arisen and surveyors must be appointed to make an Award.
What the Act does stipulate is that notice is served for notifiable works. Examples include:
- excavating within 3 metres of a neighbour's building and to a lower depth than its foundations, or within 6 metres where the excavation cuts a 45-degree line from the bottom of their foundations (Section 6)
- cutting into a party wall, for example to insert a steel beam (Section 2, served under Section 3)
- removing a chimney breast attached to a party wall
- raising or reducing the height of a party wall
- building a new wall on or astride the line of junction (Section 1)
What happens if my neighbour does not agree?
A neighbour cannot block notifiable works by refusing to agree. Dissent, or silence for 14 days, simply means a dispute exists and the Act's dispute procedure applies.
If the Adjoining Owner does not appoint a surveyor, the Building Owner can serve a further request under Section 10(4). If there is still no appointment within 10 days, the Building Owner may appoint a surveyor on the Adjoining Owner's behalf under Section 10(4)(b). That surveyor is not a mediator or an advocate; they act impartially under the Act.
Please do not assume you can begin work because your neighbour has not replied. Silence is not consent. Our guide on what to do if your neighbour ignores a party wall notice explains the steps in more detail.
What is a Schedule of Condition?
A Schedule of Condition is a written and photographic record of the parts of the Adjoining Owner's property close to the works, taken before anything starts. It typically covers ceilings, walls, floors and external elevations near the shared boundary, noting existing cracks to plaster, the condition of glazing and the state of brickwork.
It records fact only. It does not comment on the cause of any defect or suggest repairs.
Is a Schedule of Condition a legal requirement?
No. The Act does not stipulate that one must be prepared. It is, however, standard practice, and where surveyors are appointed it is normally annexed to the Party Wall Award. Going without one leaves both owners exposed if damage is later disputed. We explain this further in why a Schedule of Condition protects everyone.
How do the Award and the Schedule work together?
The Award governs the works: what can be done, how and on what terms. The Schedule records the starting point: what the neighbouring property looked like beforehand.
If damage is alleged once the works are under way or complete, the surveyors compare the property against the Schedule. Under Section 7(2) of the Act, the Building Owner compensates the Adjoining Owner for loss or damage caused by the works. The Award supplies the rules, and the Schedule supplies the evidence.
Frequently asked questions
Is a Party Wall Agreement the same as a Party Wall Award?
In everyday use, yes. "Party Wall Agreement" is the common name, but the formal document made by surveyors under the Act is a Party Wall Award.
Can I have a Schedule of Condition without an Award?
Yes. If your neighbour consents and no Award is needed, it is still sensible to arrange a Schedule of Condition before work starts.
Who prepares each document?
Both are prepared by the surveyors. Where two surveyors are appointed, the Building Owner's surveyor usually drafts them and the Adjoining Owner's surveyor checks and agrees them.
Speak to a Chartered party wall surveyor in North London
Whether your works call for a Party Wall Award, a Schedule of Condition or both, it helps to have someone who handles these documents every day.
Hudson Party Wall Surveyors is a Chartered, RICS-regulated practice based in North Finchley, acting for Building Owners and Adjoining Owners across North London. If you would like to discuss your project, call Simon on 020 3488 7747 or email simon@hudsonpartywallsurveyors.co.uk.
Need help with your Party Wall Matters?
We’re here to help. Call for free advice or book a Chartered Party Wall Surveyor to call you at your convenience.